SECTIONAL REPLACEMENT WORK ON THE LEAKING SPOTS
- Home
- Lq-project
- Sectional Replacement Work on the Leaking Spots
Brochure
Download our document to see specific data of the service and how we work.
Let’s Start Work
Together
Please feel free to contact us. We will get back to you with 1-2 business days. Or just call us now.
About Project
The detailed sectional integrity assessment projects were executed in the sequence as stated below: Mobilization of equipment and personnel from our base office at Enerhen Road to both sites (KP19 & 29) respectively Survey and flagging off of life line(s) and pegging of gas line and other existing underground facilities Site Preparation for equipment off loading at possible closest point to site of operation Cordoning off of the work areas and redirecting other route users to other safe and free routes Anchoring of A-Frames, Tug Boats and Barges closest to sport of operations Excavation of 24” line 200m upstream and 200meters downstream and floatation of A-frames in-between pipes at equal-distant positions for even pipe lifts Removal of 12 Wraps from each joints (3upsrteam and 3dowmstream) on both sites Visual Inspection and Ultrasonic Testing (UT) of the 3pipes and Joints (upstream and downstream) from leaks Demobilization of equipment and personnel from site.
Customer Wishes
NGPTC monitoring team should be highly commended for their time, effort and sacrifices to monitor all the stages of the job irrespective of weather conditions and made meaningful contributions at each stage. Client should ensure that the right drawings for a facility is available to the contractor before moving to site in other not to temper with other ground facilities. NGPTC should also be commended for properly flushing the line before the assessment work. All welded Joint should be properly wrapped and protected to specification. When lowering river crossing, optimal care should be in place to avoid kink of pipes Proper protection system should be in place to double protect pipes 6new Line 24’’ CWC pipes should be used on both sides for the river crossing.
Our Approach And Solution
The detail integrity pipeline sectional assessments were a 24’’ diameter pipe line conveying gas from Warri to Escravos. The leak points were located at KP 29~ Near Tekedor~Cosimi Communities and KP 19~ Poro Creek. The damaged sections of the first point (KP29) was a blast spot at the center of the river crossing and while the other leak point at KP 19 (Poro Creek), was as a result of Internal Corrosion of the pipe and was also confirmed by the UT result of that section.

Health Safety and Environment
- All safety procedures were strictly adhered to and all safety threats contained throughout the project.
- Standby Boats & Emergency response crew was on ground during the execution of the entire project to arrest any emergency need. Double detection and confirmation system was employed during the repairs period.
Community Affairs and Security
- There was perfect understanding and co-operations between the host communities and our company. The Community executives were duly notified and contacted to assist in engaging locals, alongside with other well respected community members who were engaged as workers during the project to handle any community issues that may arise in the course of the project.
- Adequate security arrangement was in place throughout the period of operation.
- Community personnel’s were employed / engaged for security services both day and night at both locations.